IPTO

TSO - Greece

Publication info

Status of publication

Planning to publish

Link to website

https://www.admie.gr/en/grid/user-connection/rest https://www.admie.gr/en/grid/user-connection/res-producers

Accessibility

NA

Regional Scope

Country

Spatial granularity

Nodal (substation)

Operator voltage level scope

150kV-400kV

Timeline for which HC is provided

NA

Information format

Table

Categories of grid users considered

Generation demand and storage

Type of grid connection capacity information

Requested (only generation), Reserved, Connected

Availability of API

Not provided

Update Cycles

RES Generators & Storage

  • Reserved & Connected semi annually
  • Requested monthly 

Demand 

  • Reserved, Connected semi annual
Available language

GR, EN

Hosting capacity assessment

Capacity type considered for hosting capacity information NA
Description of what firm capacity means and the aspects that structure the definition A new legislative framework introducing an explicit distinction between firm and flexible connection capacity is expected to enter into force shortly in Greece, transposing article 6a of EU Directive 2019/944. Firm capacity refers to the guaranteed injection or absorption of electricity allocated to a grid user, without network-congestion-related restrictions under normal network operating conditions. IPTO retains the right to curtail demand and/or production in order to maintain system stability and security.
Description of what flexible capacity means and the aspects that structure the definition According to the new legislative framework implementing art. 6a of Directive (EU) 2019/944, which is expected to enter into force shortly in Greece, flexible capacity refers to injection or absorption of electricity that is subject to restrictions related to local network congestion under normal network operating conditions, in accordance with the terms and conditions of the respective agreement. Flexible connection agreements are expected to primarily concern guarantees regarding the energy component rather than capacity.
Description of the methodology that leads to flexible capacity results The methodology will be defined in coordination with the Greek Energy Regulator.

Additional information for connection request and hosting capacity information

Publication status for connection request procedure

Applications for granting a grid connection offer for RES, HECHP and Storage Stations are accepted during the first ten days of each month. 

Source: Article 5 of Law 4951/2022 regarding the submission procedure of grid connection applications and the regulatory deadlines for checking application completeness.

Available options for the investors if the map shows 'no capacity available' in their interested area

Even though no map has been published, in such cases applicants usually contact the TSO directly to inquire about the available grid capacity and alternative connection opportunities. The final conditions of a connection are an outcome of the formal grid connection procedure. During the technical assessment of the application, the required works for connecting the stations to the System are determined, the cost of which is allocated in accordance with the applicable legal framework.

Connection request rules

Yes. For Demand applications, "first comes first served" rule is applied. 

Source: Priority framework for the assessment of applications for granting definitive connection offers.

Information published for volumes of connection requests/waiting lines

Partly. Pending applications for RES & HECHP plants are published monthly, whereas stations (RES & HECP & Storage) that have been granted connection offers or are operational are published semi-annually. In addition, consolidated lists of pending applications handled by IPTO and HEDNO in grid-congested areas are published periodically, in accordance with decisions issued by RAAEY (Regulatory Authority for Energy, Waste and Water). Demand plants that have been granted connection offers or are operational are published semi-annually basis.

Granularity of published connection requests/waiting lines

Regional and per Regional Unit level

Additional information

Application completeness is examined within 20 days. Financial guarantees (e.g., bank letters of guarantee) are requested in most of the cases.

Relevant references/Links/Additional material

Disclaimers, boundaries, and calculation methods
  • During the technical assessment of the applications, the operational limitations specified in Article 10 of Law 4951/2022 and the corresponding Ministerial Decision are taken into account.
Connection request process
Auxiliary documents
Legal references
  • Article 89 of Law 4951/2022, Articles 11C and 11D of Law 4685/2020, Article 30 of Law 5095/2024, alongside their respective implementing Ministerial Decisions. Includes the prioritization frameworks for RES, HECHP, standalone/co-located storage systems (BESS), pumped storage stations, corporate agricultural PPAs, and agreements with energy-intensive industries, as well as other legislation and amendments directly affecting the prioritization of application assessments. 
  • If the maximum capacity limit for issuing connection offers within a priority group is reached, the remaining applications will be reassigned to lower-priority groups, in accordance with the specific criteria and conditions applicable to each group.
Contact point for connection requests