Sadales Tikls
DSO - Latvia
Publication info
| Publication status | Published |
| Access link to GHC publication of the SO | https://karte.sadalestikls.lv/lv/briva-jauda |
| Access type | Open |
| Geographical Coverage | Country |
| Spatial granularity | Nodal (substation) |
| Voltage Level Coverage | Aiming at 6;10;20 kV network by showing the HC limits at the 6-10-20/110 kV substation |
| Time Horizon (e.g. Y+1, Y+3 / 202x / snapshot) | Snapshot |
| Data Format (Table, Map, etc.) | Map |
| Grid user types covered | Demand, generation (technology-agnostic) |
| Displayed Capacity Type (e.g. available/requested/reserved/connected etc.) |
|
| API Availability | Not Applicable |
| Grid hosting capacity downloadable & format | No |
| Update Frequency | Weekly |
| Available language | National language(s) only |
Hosting capacity assessment
| Capacity type considered for available hosting capacity information (e.g., Firm and/or Flexible) | Firm |
| Description of what firm capacity means | Required capacity available for customers 24/7 |
| Description of the aspects/methodology that leads to firm capacity results | For Generation: Installed capacity + reserved capacity. For Demand: Historical load + reserved capacity x probability of installation/commissioning |
| Main assumptions/disclaimers behind calculations |
|
Additional information for connection request and hosting capacity information
| Connection request procedure | For new demand connections: https://sadalestikls.lv/lv/pastavigs-pieslegums. For generation connections: https://sadalestikls.lv/lv/elektrostacijas-pieslegsana |
| Available options for the investors if the map shows “no capacity available” in their interested area | Applications are encouraged in any case, but especially on the demand side. Applications are assessed individually, with Sadales Tikls examining line reconfigurations, N-1 operations, and non-firm connections. |
| Connection request rules/principles | First come, first served |
| Information published for volumes of connection requests/waiting lines | Partly, available for generation |
| Granularity of published connection requests/waiting lines (e.g., nodal, regional, per SO) | Nodal (substations) |
Relevant references/Links/Additional material
For new demand connections: https://sadalestikls.lv/lv/pastavigs-pieslegums
For generation connections: https://sadalestikls.lv/lv/elektrostacijas-pieslegsana
General technical requirements for connecting a power plant: https://sadalestikls.lv/lv/visparejas-tehniskas-prasibas-elektrostacijas-pieslegsanai
General technical requirements for connecting a microgenerator: https://sadalestikls.lv/lv/visparejas-tehniskas-prasibas-mikrogeneratora-pieslegsanai
System connection rules for the electricity distribution system: https://likumi.lv/ta/id/323728-sistemas-piesleguma-noteikumi-elektroenergijas-sadales-sistemai.System connection rules for electricity producers: https://likumi.lv/ta/id/331779-sistemas-piesleguma-noteikumi-elektroenergijas-razotajiem
Grid hosting capacity map: https://karte.sadalestikls.lv/lv/briva-jauda
How to make a connection to "Sadales tikls" grid: https://sadalestikls.lv/lv/padoms/ka-ipasuma-ievilkt-elektribu
New connection fee map: https://karte.sadalestikls.lv/lv/jauna-piesleguma-maksa
Load calculation calculator: https://sadalestikls.lv/lv/slodzes-kalkulators