At the TSO level, Fingrid publishes hosting capacity information. The hosting capacities are shown by year for the next ~10 years on the substation and power line levels for Fingrid’s 110–400 kV network. The grid scope does not provide information on DSOs’ network capacities. The hosting capacities are calculated for firm capacities, and the values are only for demand and production. Calculations take into account the thermal, dynamic, and voltage limitations set by the grid for each given year. The values presented in the grid scope are rough estimates, and are not legally binding. Fingrid does not guarantee that the values in the grid scope are comprehensive and error-free. The capacity is provided on a first-come, first-served basis.