REN
TSO - Portugal
Publication info
| Status of publication | Published |
| Link to website | https://mercado.ren.pt/PT/Electr/AcessoRedes/AcessoRNT/CaractRNT |
| Accessibility | Open |
| Regional Scope | Country (Portugal) |
| Spatial granularity | Nodal (substation) |
| Operator voltage level scope | 150 kV, 220 kV, and 400 kV |
| Timeline for which HC is provided | Short term (now) and long term (10 years) |
| Information format | Table |
| Categories of grid users considered | Generators only |
| Type of grid connection capacity information | Firm capacity (capacity available all the time except in rare exceptional situations) |
| Update Cycles | Yearly |
| Available language | National language(s) only |
Hosting capacity assessment
| Capacity type considered for hosting capacity information |
Firm |
| Description of what firm capacity means and the aspects that structure the definition |
“Firm capacity” means that it is available all the time except in rare exceptional situations. In some cases, power plants may be unable to produce not due to network constraints, but because of market conditions, such as excess generation compared to demand. |
| Description of what flexible capacity means and the aspects that structure the definition |
For now, “flexible capacity” is not calculated/published. |
| Description for the criteria and methodologies used that lead to the published information |
Capacities are estimated based on a set of scenarios concerning network operation conditions in different time horizons, considering the N, N-1, and N-2 criteria defined in the regulation. |
| Main assumptions/disclaimers behind calculations |
Long-term capacity only takes effect after approval and entry into service of the specific reinforcements foreseen in the Portuguese TYNDP. The published capacities do not include information on substation bay availability. |
| Additional information |
The attribution of capacity is managed by the Portuguese General-Directorate for Energy and Geology. |
Additional information for connection request and hosting capacity information
| Connection request procedure |
The procedure for access to the National Electricity Transmission Network (RNT-E) by electricity generation centres is based on the provisions of Decreto-Lei nº 15/2022, in its current wording. Under Article 18 of the aforementioned Decreto-Lei, the allocation of injection capacity reservation in the Rede Elétrica de Serviço Público (Public Service Electrical Grid) (RESP) is formalised through a Título de Reserva de Capacidade de Injeção (Title of Reserved Injection Capacity; ) (TRC), issued by the network operators, in this case by the TSO, under the following modalities:
For more information, please refer to consult the DGEG portal. After obtaining the TRC, the applicant must request from the TSO the connection conditions of the electricity generation centre to the RNT-E. The TSO will present a technical-commercial proposal defining deadlines and associated costs, as well as technical connection conditions, as established in the Regulamento de Relações Comerciais (RRC). The procedure for access to the National Electricity Transmission Network (RNT-E) by electricity generation centres is based on the provisions of Decreto-Lei nº 15/2022, in its current wording. Under Article 18 of the aforementioned Decreto-Lei, the allocation of injection capacity reservation in the Rede Elétrica de Serviço Público (Public Service Electrical Grid) (RESP) is formalizeised through a Título de Reserva de Capacidade de Injeção (Title of Reserved Injection Capacity; ) (TRC), issued by the Network network Operatorsoperators, in this case by the TSO, under the following modalities:
For more information, please refer it is recommended to consult the DGEG portal. After obtaining the TRC, the Applicant must request from the TSO the connection conditions of the electricity generation centercentre to the RNT-E. The TSO will present a technical-commercial proposal defining deadlines and associated costs, as well as technical connection conditions, as established in the Regulamento de Relações Comerciais (RRC). The electricity generation centre is subject to the provisions of the European connection code RfG and Portaria n.º 73/2020, de 16 de março. For compliance verification purposes, the electricity generation centre is subject to operational communication procedures established for production units, available on the TSO website: Procedimentos Verificação Conformidade. Formal requests to connect a demand facility to the RNT-E should be submitted to acessorede@ren.pt and must include the following information:
Once this information is received, the connection request will be evaluated by REN regarding the availability of supply capacity and technical connection conditions, according to the chronological order of submission. If there is a high number of connection requests for demand facilities to the RESP and insufficient supply capacity within the required deadlines, the government member responsible for energy may determine the opening of Zonas de Grande Procura, where the allocation of supply capacity is governed by an exceptional procedure, as established in Decreto-Lei n.º 120/2025. Additionally, after the requested supply capacity is allocated, the applicant must request from the TSO the technical connection conditions of the demand facility to the RNT-E. The TSO will present a technical-commercial proposal defining deadlines and associated costs, as well as technical connection conditions, as established in the Regulamento de Relações Comerciais (RRC). All requests for information or clarifications regarding access to the National Electricity Transmission Network (RNT-E) for Producers or Consumers may be addressed to macessorede@ren.pt. |
| Information published for volumes of connection requests/waiting lines |
Yes |
| Granularity of published connection requests/waiting lines |
Per node, per technology |
| Additional information |
Information published for volumes of connection requests/waiting lines only for generators |
Relevant references/Links/Additional material
- The amount of power associated with connection requests that have been authorised but not yet in service are published every year in the “Caracterização da Rede Nacional de Transporte para Efeitos de Acesso à Rede” and in the Portuguese TYNDP every 2 years.