Tennet

TSO - Germany

Publication info

Status of publication

Published

Link to website

https://www.tennet.eu/de/strommarkt/kunden-deutschland/netzanschlussanfragen

Accessibility

Open

Regional Scope

Control zone (extra high voltage only)

Spatial granularity

Only substations with available (future) connection capacity are shown.

Operator voltage level scope

220 kV, 380 kV

Timeline for which HC is provided

Potential commissioning years: 2030 - 2036

Information format

Map and Table

Categories of grid users considered

Demand and storage

Type of grid connection capacity information

Availability

Availability of API

Not provided

Update Cycles

Based on the grid connection procedure cycles: currently every 10 months

Available language

National language(s) only

Hosting capacity assessment

Capacity type considered for hosting capacity information

Firm

Description of what firm capacity means and the aspects that structure the definition

Firm capacity for demand means maximum admissible grid usage (offtake) subject to the contracted capacity (three-phase effective power) and connection rules (ramping, harmonics etc.). In general, no further operational constraints are applied, also not temporal. For generation and storage units, firm capacity refers to the contracted maximum three-phase effective power of feed-in or offtake (for storage units). (Temporal) operational restrictions (imposed redispatch orders) must be complied with. Compensation schemes are applied.

Description of the methodology that leads to firm capacity results

Under development

Description of what flexible capacity means and the aspects that structure the definition

Currently not applicable.

Description of the methodology that leads to flexible capacity results

Not provided

Description for the criteria and methodologies used that lead to the published information

Available switch bays and potential built outs (with secured land rights) have been considered, reserverations were deducted. Further, the already connected units and transformers to the distribution grid have been considered to check for potential violations of the maximum load and generation that can be connected to a busbar (“3 GW criterion”). Prominent short-circuit-related restrictions have been considered as well.

Main assumptions/disclaimers behind calculations

The simulation results are indicative and not legally binding. Further in-depth studies are required during the grid connection process, e.g. regarding short-circuit capacity.

Additional information for connection request and hosting capacity information

Connection request procedure

Explained on the following page: https://www.tennet.eu/de/strommarkt/kunden-deutschland/netzanschlussanfragen

Options available for the investors if the map shows 'no capacity available' in their interested area

Subject to project specific studies, longer lead times (several years) are likely. Please contact netzanschlussanfragen@tennet.eu.

Connection request rules

Other (please specify)

Information published for volumes of connection requests/waiting lines

No

Granularity of published connection requests/waiting lines

NA

Additional information

First-ready-first-serve procedure for demand and storage units, based on maturity score, with application window. For powerplants, the connection procedure is determined in the Ordinance on the Regulation of the Grid Connection of Installations for the Generation of Electrical Energy (KraftNAV, "first-come-first-serve"). For renewable energy sources, the connection procedure is determined in the Law for the Expansion of Renewable Energies (EEG, "first-come-first-serve").

Relevant references/Links/Additional material

Legal references

Please refer to the references listed on our website

Contact point for hosting capacity information
Contact point for connection requests
Additional information

Connection request process: Please read the accompanying text carefully and contact us in case of unclearities.