APG

TSO - Austria

Publication info

Status of publication Published
Link to website https://markt.apg.at/netz/netzanschluss/netzanschlusskapazitaeten/
Accessibility Open
Regional Scope Country
Spatial granularity Nodal (substation)
Operator voltage level scope 110 kV, 220 kV, 380 kV
Timeline for which HC is provided 2030
Information format Table
Categories of grid users considered Generators and demand
Type of grid connection capacity information Firm and flexible connections
Availability of API No
Update Cycles Monthly
Available language National language(s) only
Additional information The published hosting capacity values are for informational purposes only and do not constitute a binding commitment by APG. They do not imply any guarantee of actual grid availability, nor do they entitle any party to reserve capacity or claim priority for grid connection. All connection requests remain subject to individual technical assessments and regulatory procedures.

Hosting capacity assessment

Capacity type considered for hosting capacity information

Firm and flexible

Description of the methodology that leads to firm capacity results

Firm capacity refers to a grid connection that can be utilised at 100% of its rated power throughout the entire year without any congestion-related restrictions.

Description of the methodology that leads to flexible capacity results

A flexible connection allows APG to temporarily limit grid usage during periods of congestion that could affect grid stability.

Description for the criteria and methodologies used that lead to the published information

APG calculates hosting capacities using a power transfer distribution factor (PTDF)-based methodology, which evaluates the impact of additional injections or withdrawals on critical grid elements. The analysis is based on the most recent TYNDP data available for the current year. A substation is assigned a hosting capacity of 0 MW (for either generation or consumption) if there is at least one hour in the year where an additional connection would exacerbate an existing congestion or create a new congestion under N-0 or N-1 security conditions. The methodology applies uniformly across the generation, demand, and storage categories. The analysis is static in nature, focusing on steady-state power flow impacts rather than dynamic or short-circuit behaviour. Hosting capacities are published per substation and reflect the firm connection potential, i.e. capacity that can be used without restriction throughout the year. The approach is independent of the grid user profile. The only distinction is between firm connection and flexible connection.

Main assumptions/disclaimers behind calculations

The published hosting capacities reflect the amount of additional power that can be either injected into or drawn from the grid without causing congestion or negatively impacting grid stability. If a firm connection is not feasible – meaning that even for a single hour in the year, an additional connection would compromise grid performance – flexible connection options may still be available. In such cases, APG retains the right to temporarily limit the connection’s power during critical periods to ensure grid security. 

According to Article 50(4a) of Regulation (EU) 2019/943 on the internal electricity market, as amended by Regulation (EU) 2024/1747, TSOs are required to publish information on available grid connection capacities and update this information monthly. The published table provides information on available and requested grid connection capacities, as well as on the possibility of flexible connections to APG’s transmission network. The published values were determined in accordance with the grid compatibility assessment procedure as outlined in our General Grid Conditions. 

At present, no unrestricted grid connection capacities are available in APG’s transmission network. Depending on the specific connection situation, an unrestricted grid connection may be granted – as an exception and subject to a positive grid compatibility assessment – for non-interruptible end consumers who pay grid usage fees in accordance with § 5 para. 1, items 1–7 of the SNE-V 2018. The column “Flexible Connection Possibility” indicates whether a limited (flexible) grid connection may be requested. Such a connection may be granted subject to a positive grid compatibility assessment. According to § 44 para. 1 of the ElWOG, the right to connect to the grid within a distribution network area generally lies with the DSOs. A direct connection to APG’s transmission network is possible only if the relevant DSO waives this right. Exceptions apply to grid users who supply electricity or are to be supplied with electricity at a nominal voltage above 110 kV. In this case, a minimum capacity of 200 megawatts (MW) is required, as stipulated in § 55 para. 7, item 5 of the ElWOG. The published hosting capacity values are indicative only and do not constitute a binding commitment for grid connection. They are based on model-based analyses using the most recent available data and reflect the current state of the transmission system under standard assumptions. Key limitations include:

  • Values are updated monthly and may change due to evolving grid conditions, new connection requests, or infrastructure developments.
  • The analysis is based on static grid models and does not account for all real-time operational constraints or dynamic behaviours.
  • A positive hosting capacity value does not guarantee a firm or flexible connection. Each request is subject to a detailed, case-specific grid compatibility assessment.
  • The values refer to the transmission grid only and do not consider potential limitations in the underlying distribution networks.

Additional information for connection request and hosting capacity information

Connection request procedure To initiate a grid connection, the grid user must submit a formal request - typically via letter - to APG. Once received, the request undergoes a comprehensive evaluation, which includes:
  • Asset assessment
  • Grid impact analysis
  • Short-circuit analysis
Following this evaluation, APG provides a formal response to the applicant within 6 months. If the connection is deemed feasible, the applicant must then make a prepayment of €1,000 per MW of requested capacity. Upon receipt of this payment, the detailed planning phase begins. For more information, please refer to the following resources: Link: https://markt.apg.at/netz/netzanschluss/ Link to the General Terms and Conditions: https://pb1-medien.apg.at/im/dl/pboxx-pixelboxx-28816/f,p/ANB_APG_g%C3%BCltig%20ab%2001.11.2024.pdf"
Options available for the investors if the map shows 'no capacity available' in their interested area If the hosting capacity table indicates that no capacity is currently available at a specific substation, investors have several options:
  • Some substations may offer a flexible connection option. This allows for grid connection under certain operational conditions, such as curtailment during congestion periods. These options are typically indicated in the published data.
  • Depending on the specific connection situation, an unrestricted grid connection may be granted – as an exception and subject to a positive grid compatibility assessment – for non-interruptible end consumers who pay grid usage fees in accordance with § 5 para. 1, items 1–7 of the SNE-V 2018.
Connection request rules Application window
Information published for volumes of connection requests/waiting lines Yes
Granularity of published connection requests/waiting lines Regional, no technological distinction (only generation versus consumption)
Additional information APG - Assets Department: https://markt.apg.at/netz/netzanschluss/

Relevant references/Links/Additional material

Calculation method, disclaimers, and boundaries
Connection request process
Contact point for hosting capacity information
Contact point for connection requests